Contract modifications and change orders

← All Insights

In short

  • Only contracting officers acting within their authority may modify contracts.
  • A unilateral modification is signed only by the contracting officer.
  • The contractor must continue performance as changed.
Published28 October 2026
Last reviewed28 October 2026
Sources current as of28 October 2026

1. Modifications and the terms that define them

Subparts 43.1 and 43.2 of the Federal Acquisition Regulation (FAR) cover contract modifications and change orders. An administrative change is a written, unilateral change to a contract that leaves the substantive rights of the parties unaffected, such as a change in the paying office or in the appropriation data (FAR 43.101).

A solicitation amendment, change order or administrative change takes its issue date as its effective date (FAR 43.101). For a supplemental agreement, it is the date agreed upon by the contracting parties.

2. Who may modify a contract

The power to execute modifications for the Government rests only with contracting officers acting within the scope of their authority (FAR 43.102(a)). Other Government personnel shall not execute modifications. They shall not act in a way that causes the contractor to believe they have authority to bind the Government. They shall not direct or encourage the contractor to do work that ought to be covered by a modification.

Modifications shall be priced before they are executed, even changes that could be issued unilaterally, if that is possible without adversely affecting the Government’s interest (FAR 43.102(b)). Where a significant cost increase could result and time does not allow price negotiation, a ceiling price at minimum shall be negotiated, unless that is impractical.

3. Bilateral and unilateral modifications

A bilateral modification, also called a supplemental agreement, is signed by the contractor and the contracting officer (FAR 43.103(a)). It is used to make negotiated equitable adjustments resulting from a change order, to definitize letter contracts, and to reflect other agreements of the parties modifying contract terms.

A unilateral modification is signed only by the contracting officer (FAR 43.103(b)). It is used, for example, to make administrative changes, to issue change orders, and to issue termination notices. It is also used for changes authorized by clauses other than a changes clause, such as the Property, Options or Suspension of Work clauses (FAR 43.103(b)).

4. Changes the contractor believes occurred

A contractor may consider that the Government has made, or may make, a change that has not been identified as such in a writing signed by the contracting officer (FAR 43.104(a)). It is necessary for the contractor to give the Government written notice as soon as possible. This permits the Government to evaluate the alleged change and confirm it, direct the mode of further performance and plan for funding. The Government may instead countermand the alleged change, or tell the contractor that it considers no change to have occurred (FAR 43.104(a)).

The clause at 52.243-7, Notification of Changes, incorporates this policy. It requires prompt notice from the contractor of any Government conduct the contractor considers a change to the contract (FAR 43.104(b)). A clause substantially the same may be inserted by the contracting officer, mainly in negotiated supply or research and development contracts for major weapon systems or principal subsystems (FAR 43.107). It shall not be used where the expected contract amount is under $1,000,000, unless the contracting officer anticipates that a contractor may allege changes other than those identified in a writing the contracting officer signed.

5. Funding a modification

The contracting officer shall obtain a certification of fund availability before executing any modification that causes or will cause an increase in funds. Modifications to contracts conditioned on availability of funds, or containing a limitation of cost or funds clause, are excepted (FAR 43.105(a)).

6. Change orders

Government contracts generally include a changes clause (FAR 43.201(a)). Under it, the contracting officer may make unilateral changes in designated areas that fall within the contract’s general scope. Unless otherwise provided, the change is a written order on Standard Form 30, Amendment of Solicitation/Modification of Contract (SF 30) (FAR 43.201(a)). The contractor must continue performance as changed (FAR 43.201(b)). In cost-reimbursement or incrementally funded contracts, however, the contractor need not continue performance or incur costs past the limits set by the Limitation of Cost or Limitation of Funds clause.

Under unusual or urgent circumstances, a change order may be issued electronically by the contracting officer, without an SF 30 (FAR 43.201(c)). The message must contain substantially the SF 30 information, and immediate action must be taken to issue the SF 30. Change orders shall come from the contracting officer, except where an administrative contracting officer holds delegated authority (FAR 43.202).

7. Accounting for changed work

Accounting systems at contractors are seldom designed to segregate the costs of changed work (FAR 43.203(a)). Before offers are submitted, the contracting officer should advise prospective contractors that their accounting procedures may need revision. The revision concerns meeting the Change Order Accounting clause at 52.243-6 and its cost segregation requirements (FAR 43.203(a)). Direct cost categories that normally are segregable under the clause include nonrecurring costs, costs of distinct work added because of the change order, and costs of recurring work (FAR 43.203(b)).

8. Documenting and definitizing a change order

When change orders are not forward priced, two documents are required (FAR 43.204(a)). They are the change order itself and a supplemental agreement that reflects the equitable adjustment which results. If the adjustment can be agreed in advance, only a supplemental agreement need be issued. Administrative changes and changes under a clause giving the Government a unilateral right, such as an option clause, initially require only one document (FAR 43.204(a)).

Equitable adjustments arising from change orders shall be negotiated by contracting officers in the shortest practicable time (FAR 43.204(b)(1)(i)).

To avoid later controversies, the contracting officer should see that every element of the equitable adjustment has been presented and resolved. The supplemental agreement should include a release similar to the sample in the section. It releases the Government from further equitable adjustments for the same facts or circumstances, except as listed (FAR 43.204(c)).

9. Changes clauses by contract type

For a contemplated fixed-price contract for supplies, the contracting officer shall insert the fixed-price Changes clause at 52.243-1 in solicitations and contracts, with alternates for services and other situations (FAR 43.205(a)). The contracting officer shall insert the Changes clause at 52.243-2 when a cost-reimbursement contract for supplies is contemplated (FAR 43.205(b)). Administrative contracting officers and the other functions of contract administration offices are covered in contract administration functions.

Key terms

Administrative changeA written, unilateral contract change that leaves the substantive rights of the parties unaffected.
Bilateral modificationA contract modification, also called a supplemental agreement, signed by the contractor and the contracting officer.
Unilateral modificationA contract modification signed only by the contracting officer.
Change orderA written order from the contracting officer making a unilateral change within the general scope of the contract.
Notification of Changes clauseThe clause at 52.243-7, which requires the contractor to notify the Government promptly of Government conduct it considers a change to the contract.

Every statement above links to the document behind it. The full source list for this piece is on the sources page.

This page describes public United States government programs for general information. It is not legal, regulatory or procurement advice, and it does not address the facts of any particular case.

How Sentfore supports this

Tracking modifications keeps contract records current. Sentfore provides business process outsourcing (BPO) support managed from McLean, Virginia: translation and transcription, document and compliance work, proposal and contract administration support, and remote paralegal and back-office support. Requirements can be sent through the contact page.